Details of the $85 million Coromandel Peninsula roading resilience programme have been released, which includes upgrading the single-lane Manaia River bridge next year.
In the same timeframe is the Owera Bridge also on State Highway 25 near the Matarangi turnoff.
Local Member of Parliament, Scott Simpson, described the announcement as being good news from the New Zealand Transport Agency.
Two programmes of work are being progressed, funded through Budget 2026 and longer-term Crown resilience funding, these include a range of bridge, culvert and drainage improvements, embankment and slope stabilisation works.
Budget 2026 did include $20 million for targeted SH25 resilience improvements and $65 million to replace the SH26 Kirikiri Stream Bridge at Kōpū. Detailed design and timeframes are being confirmed for that work.
For the SH25 improvements NZTA intend to progress the Manaia and Owera sites from mid-next year, pending detailed design.
There are four other sites that have been identified at Whenuakite, Waikawau, Te Kouma Hill and Whangapoua Hill. Five further sites will be rolled out over the next four years.
Between March and July 2027, NZTA intend to deliver nine sites as part of the Crown-funded resilience programme. These include under slip and over slip rockfall protection on the Thames Coast Road between Ruamahanga and Tapu, along with sites near Whakatete and Kereta.
Under slip treatment will continue SH2 in the Karangahake Gorge near Waikino. Simpson said prioritised sites across both packages of work regularly experience landslides, rockfall and drainage issues.
“Treatments may include retaining works, drainage upgrades, slope stabilisation and road protection works. All the above sites are at various stages of verification, design and consenting requirements, ahead of appointing contractors to carry out the work.
“Access and reliability are critical for Coromandel communities and businesses, particularly over busy visitor periods.
“Resilience work to be completed this construction season is expected to start work after Waitangi Day to minimise delays and disruption. This resilience work also sits alongside recovery works following January storms, bridge replacements at Tairua and Ramarama, and the general road maintenance programme currently underway on the network.
“While this resilience work will not remove every risk or prevent all future disruption, it will reduce risk at priority locations and make state highway connections around the Peninsula better prepared for severe weather.”
The map shows the identified sites across both programmes and including priority bridge replacements currently underway and a storm recovery site that will be completed this season at Kuaotunu.